Time bars in Western Australia subcontracts: what you lose, and when

A time bar is a clause that extinguishes your claim - for an extension of time, a variation, or delay costs - unless written notice is given within a stated window. In every subcontract we've analysed where the drafting was identifiable, the time bars were absolute: miss the window and the entitlement is gone, not reduced. Your Building and Construction Industry (Security of Payment) Act 2021 (WA) payment claim rights survive contractual time bars, but your contractual entitlements don't.

How the clause actually works

The typical drafting makes notice a condition precedent: no notice in time, no entitlement - regardless of merit, regardless of whether the builder caused the delay. Notice windows in the contracts we've analysed run as short as 2 business days for variations and cluster around 5 business days for extensions of time.

The trap isn't the paperwork, it's the trigger: the clock usually runs from when the delay or direction occurred, not from when its cost became clear. A site conversation doesn't stop it. Only written notice in the form the contract requires does.

What Western Australia law does and doesn't rescue

The Building and Construction Industry (Security of Payment) Act 2021 (WA) can't be contracted out of: your right to serve a payment claim, and the builder's obligation to answer it with a payment schedule within 15 business days, survive whatever the contract says. But an EOT entitlement extinguished by a contractual time bar is hard to revive anywhere - the Act protects the payment process, not the underlying contractual entitlement.

Two regimes run in parallel: contracts entered into from 1 August 2022 sit under the 2021 Act (East Coast model), while older contracts stay under the Construction Contracts Act 2004 with its 90-business-day adjudication window - the contract date decides which set of rules you're under.

The habit that beats the clause

You won't negotiate every time bar out. The operating fix is a standing habit: written notice the day anything changes - a delay starts, a direction lands, scope moves - before the ute leaves site. One short email that anchors the date, flags the claim, and says the formal notice follows.

Before signature, the positions worth asking for: a longer window (10 business days is defensible; builders have accepted more), notice as a requirement rather than a bar, and one notice per event rather than rolling updates.

From the Australian Subcontract Index - live data
100%
have time bars that extinguish the claim entirely · 39 of 39
From 54 subcontracts analysed to date · see the full Index
Where does your contract sit?

Clause-by-clause risk report against Western Australia security of payment law in about 90 seconds.

Scan my subcontract free

Frequently asked questions

Can a time bar in a WA subcontract really extinguish a claim the builder caused?

Yes, and it's the standard drafting - the clause operates on notice, not fault. Courts enforce clear conditions precedent. The protection is operational: written notice inside the window, every time.

Do time bars stop me making a payment claim under the Act?

No - the Building and Construction Industry (Security of Payment) Act 2021 (WA) can't be contracted out of, and your payment claim rights survive. But the Act protects the payment process; a contractual EOT entitlement lost to a time bar doesn't come back through adjudication.

Keep reading
What is a time bar in a subcontract — and when does it kill the claim?How many days to notify an EOT claim is normal?Do variations need to be in writing for me to get paid?How long can a builder take to pay a subcontractor in Western Australia?Retention on Western Australia subcontracts: what's normal, and what to watchHow adjudication works in Western AustraliaNot being paid in Western Australia: when can you lawfully stop work?Variations on Western Australia subcontracts: getting changed work paid

General information for Australian subcontractors, not legal advice. Statutory deadlines change and have exceptions - verify against the Act and current guidance, or with a construction lawyer, before acting on them.