TCCC
The Construction Contracts Co.
Subcontract Guides
All guides
Time bars & EOT

How many days to notify an EOT claim is normal?

Five business days is the aggressive-but-common market norm for notifying an extension of time claim in Australian subcontracts; anything shorter is high risk, and a clause that extinguishes the EOT entirely for late notice is critical risk. The EOT window matters because it prices the liquidated damages clause: an EOT you're barred from claiming becomes delay you're paying for.

Why the EOT clause is really a money clause

An extension of time isn't just programme relief. It's your defence to liquidated damages. When rain, redesign or another trade's delay pushes you late, the EOT is what stops the LD clock running against you. A 3-business-day absolute bar on EOT notices, sitting next to an uncapped $2,000/day LD clause, is a machine for converting other people's delays into your liability.

Watch for stacked requirements too: some clauses demand an initial notice within days, then a fully particularised claim with programme analysis shortly after, each with its own bar. Every extra hurdle is another way a valid entitlement dies on paperwork.

The position to negotiate

Ten business days for the initial notice is a reasonable target, with the detailed particulars to follow within a further period. Push for notice as a requirement rather than a condition precedent, and for the builder's actual knowledge of the delay event to satisfy the notice. If none of that lands, the fallback is operational: notify everything, in writing, immediately.

Screwed Down by Mat Kennedy
Go deeper · from the book
Chapter 2 of Screwed Down: Two words that kill more claims than bad work ever will
What it costs you in dollars, the clause to ask for, and what to do on Monday.
Read the chapter summary →Get the book on Amazon

Know where your contract stands

Clause-by-clause risk report against your state's Security of Payment laws in about two minutes.

Scan my subcontract free
Free · no account · confidential

Common questions

What delays justify an EOT?

Whatever the clause says. That's the point. Check which causes qualify (weather, principal-caused delay, latent conditions, variations) and which are excluded. A short qualifying list plus a tight time bar narrows your protection from two directions at once.

Can I claim delay costs as well as time?

Time and money are usually separate entitlements with separate notice requirements: an EOT extends the date, while delay damages compensate the cost, often only for a subset of causes. In Victoria, note the Act was reformed from 15 April 2026: time-related costs that were once 'excluded amounts' can now generally be pursued at adjudication.

Time bars and notice windows, by state

QueenslandNew South WalesVictoriaWestern AustraliaSouth AustraliaTasmaniaAustralian Capital TerritoryNorthern Territory

Keep reading

Free 7-day email course
Learn to read a subcontract like a contracts specialist
One short email a day for seven days: time bars, LDs, retention, set-off, variations, and what to negotiate before you sign. Then it stops. No newsletter, no follow-up sequence, one-click unsubscribe.

General information for Australian subcontractors, not legal advice. Statutory deadlines and details vary by state and change over time; verify them before relying on them. Written by Mat Kennedy at The Construction Contracts Co.