How long does the builder have to respond to your payment claim?
Under the Security of Payment Acts, a respondent must serve a payment schedule within 10 business days of your claim in NSW, VIC, TAS and the ACT, and within 15 business days in QLD, SA and WA — silence makes the full claimed amount a debt due. The NT runs a different model with a 90-day adjudication window. Pick your state and your claim date to see your timeline.
The statutory windows, state by state
Common questions
How long does a builder have to respond to a payment claim?
On the East Coast Security of Payment model, the respondent must serve a payment schedule within 10 business days of the claim in NSW, VIC, TAS and the ACT, and within 15 business days in QLD, SA and WA — or any shorter period the contract sets. The NT runs a different model with no schedule exchange.
What happens if the builder doesn't respond at all?
Silence within the statutory window makes the full claimed amount a debt due, and bars the respondent from raising reasons against it at adjudication — one of the strongest positions a subcontractor can hold. Verify the exact deadline (public holidays extend business-day counts) before acting on it.
How are business days counted under the Security of Payment Acts?
Business days exclude weekends and public holidays, and the Acts also exclude certain end-of-year periods. That's why this checker labels every computed date as the earliest possible — the real deadline can only be later. Verify the exact date under your state's Act before relying on it.
How long do I have to apply for adjudication?
It depends on the state and the trigger — typically around 10 business days from receiving a disputing payment schedule on the NSW-style Acts, generally 30 business days for a standard QLD application, and 90 days from the payment dispute arising in the NT (90 business days under WA's pre-2022 Act). The windows are short and strict, which is why checking your position early matters.
Keep reading
General information, not legal advice. Computed dates are the earliest possible (weekends excluded only); public holidays, the Acts' end-of-year exclusions and contract terms can change real deadlines — verify before acting. Nothing you enter here is uploaded or stored. Built by Mat Kennedy at The Construction Contracts Co.