Structural steel subcontracts: the risks and what to negotiate
Structural steel packages carry shop drawing approval, fabrication lead time and erection on the critical path. The contract decides who wears approval delays, design changes after fabrication starts and price movements in steel.
AI risk report, not legal advice. The scanner gives general information about the risks in a document. It is not a lawyer, does not know your circumstances, and can be wrong. For decisions with legal consequences, get advice from a construction lawyer.
Where structural steel subcontractors lose money
Shop drawing approval delays
Fabrication can't start until shop drawings are approved. If the contract has no timeframe for the builder's review, approval delays become your programme risk. Ask for a review period and an extension of time when it is exceeded.
Design changes after fabrication
A change after steel is cut means scrap, re-fabrication and re-delivery. Make sure changes after approval are variations, including material already fabricated.
Material price escalation
Steel prices can move between tender and fabrication. On long jobs, a rise-and-fall clause or a fixed validity period for your price protects the margin.
Erection dependencies
Erection needs cranes, access and completed footings from others. Interruptions caused by those trades should be delay events.
Three things to push for in your departures schedule
- A fixed review period for shop drawings with an extension of time if exceeded
- Changes after shop drawing approval paid as variations, including fabricated material
- Price validity or rise-and-fall for steel on longer programmes
The free scanner finds these clauses in your actual contract in about two minutes and writes the departures schedule for you.
What the Index says
Live figures from the Australian Subcontract Index, 90 real subcontracts. The Index holds only 4 structural steel contracts so far, under the 10-contract threshold, so these are national figures across all trades. Nothing under 10 contracts is ever shown.
Structural steel subcontracts by state
Structural steel subcontracts: common questions
Who pays if the design changes after steel is fabricated?
Under a well-drafted subcontract, the builder, as a variation covering the fabricated material, re-fabrication and re-delivery. Check that approved shop drawings fix the design for the purposes of variations.
Do structural steel subcontractors have payment rights that override the contract?
Yes. Every state and territory has a Security of Payment Act that lets you make a payment claim and get to adjudication quickly, and several states cap how long payment terms can be. The state pages below set out each one.
Is the scanner free?
Yes. No account, no card. Upload the subcontract and the full report appears in about two minutes. General information, not legal advice.