The Construction Contracts Co.
Queensland Subcontract Guides
QLD scanner
Queensland · adjudication

How adjudication works in Queensland

Adjudication is the fast, binding-for-now determination of a payment dispute under the Building Industry Fairness (Security of Payment) Act 2017 (QLD) - built for cash flow, not courtroom perfection. In Queensland, applications go generally 30 business days from the relevant trigger for a standard application, lodged with the QBCC. The strongest position a subcontractor can hold is a valid payment claim the builder never answered with a payment schedule: the full amount becomes payable and the builder's defences are barred.

The sequence

A valid payment claim starts everything. The builder has 15 business days to serve a payment schedule saying what it will pay and why. From there, two roads: a schedule that disputes your claim leads to an adjudication application; no schedule at all makes the full amount a debt due - and in that case the builder is barred from raising its reasons before the adjudicator.

Adjudication applications go to the QBCC Adjudication Registry rather than a private nominating authority, and if the builder misses the payment schedule deadline it becomes liable for the full claimed amount and is barred from raising reasons at adjudication.

What wins at adjudication

Adjudicators decide quickly and on the documents. The winning inputs are boring: a claim that identifies the work and the amount, served on time to the right party; contemporaneous records - site diaries, notices, delivery dockets, emails anchoring dates; and a claimed amount built up transparently.

Most of that is decided months earlier, on site, by habit. The subbies who win at adjudication are the ones whose paperwork was already in order when the dispute started.

Where to apply

QBCC Adjudication Registry. QLD adjudication applications are lodged with the QBCC, not a private nominating authority.

Exact deadlines and application mechanics should be verified against the Act and current guidance before filing - they're strict, and a defective application wastes the strongest lever you have. Official guidance: https://www.qbcc.qld.gov.au/payment-disputes

Where does your contract sit?

Claim Pro - likelihood of success, the builder's likely defence, and next steps under Queensland law.

Assess my payment dispute free

Frequently asked questions

How long does adjudication take in QLD?

Determinations typically land within about 10 business days of the adjudicator accepting the application - the regime is built to move at cash-flow speed, not litigation speed.

Do I need a lawyer to adjudicate?

No - the regime was designed for parties to run themselves, and many subcontractors do. For larger or messier disputes a construction lawyer's review of the application is cheap insurance. Either way, the evidence that decides it is the paperwork you kept on site.

Keep reading
How does adjudication actually work?What makes a progress claim one that actually gets paid?Can I suspend work if I'm not being paid?How long can a builder take to pay a subcontractor in Queensland?Time bars in Queensland subcontracts: what you lose, and whenRetention on Queensland subcontracts: what's normal, and what to watchNot being paid in Queensland: when can you lawfully stop work?Variations on Queensland subcontracts: getting changed work paid

General information for Australian subcontractors, not legal advice. Statutory deadlines change and have exceptions - verify against the Act and current guidance, or with a construction lawyer, before acting on them.