AS 4902 design and construct contracts: what the form says and how it is usually amended
AS 4902-2000 is the design and construct sibling of AS 4000. The clause structure is largely the same, with one large addition: the contractor takes responsibility for design as well as construction. For a subcontractor that matters more than it sounds, because design risk does not stay with the builder. It is pushed down to the trades whose work it touches, often to trades who priced install only. The form is copyright Standards Australia, so this page describes it rather than reproducing it.
What the drafting says
Figures read from publicly published documents analysed in the Australian Subcontract Index corpus, August 2026.
How it compares
The amendment pattern is the same one the Index records across subcontracts: notice clauses converted to absolute bars, set-off without notice, termination for convenience added.
The design and construct twist is a fourth pattern: design warranties widened, then passed down word for word to subcontractors whose scope and price never included design.
What to do about it
Common questions
What is AS 4902?
AS 4902-2000 is the Australian Standard general conditions of contract for design and construct projects. The contractor is responsible for both design and construction, and the contract is administered by a Superintendent.
How do you draft an AS 4902 contract?
You do not rewrite the form; you buy it from Standards Australia and build around it. An AS 4902 contract is assembled from four parts. The general conditions are the printed form and stay as published. Annexure Part A is where the project particulars go: the principal and contractor, the date for practical completion, the liquidated damages rate, security and retention, the defects liability period, the insurance limits and the superintendent. Annexure Part B (or a separate schedule of special conditions) lists every amendment to the general conditions by clause number, and this is where the risk moves. Then the contract documents are scheduled: the principal's project requirements, the preliminary design, the tender and any drawings, in an order of precedence. A drafter working for a principal spends most of the effort in Part B; a trade reading one should spend most of theirs there too.
How are AS 4902 contracts usually amended?
The common amendments strengthen the design warranties, convert notice requirements into time bars, delete the Superintendent's discretion to extend time, add termination for convenience and widen set-off. The annexure then fills in the project figures: security, liquidated damages and the defects period.
Which subcontract goes with AS 4902?
AS 4903-2000 is the companion subcontract. In practice many builders use their own template instead and copy the design obligations across.
I only install. Can a design and construct subcontract make me liable for design?
It can if you sign it unamended. Liability follows the words, not the quote. Have the scope state that you carry no design responsibility, and have the design warranties removed or limited before signing.
Keep reading
- What should I check before signing a subcontract? →
- What is a time bar in a subcontract, and when does it kill the claim? →
- What does termination for convenience mean in my subcontract? →
- The QBCC commercial template →
- AS 4901, as amended →
- The builder's own template →
- Purchase order terms →
- AS 4000 (head contract) →
- AS 4903 (design and construct subcontract) →
- AS 2545 (older subcontract form) →
- The MBA NSW standard trade contract →
- All contract-form breakdowns →
General information for Australian subcontractors, not legal advice. Patterns describe publicly published documents analysed in the Index corpus, and standard forms are described from their published, unamended editions; the document you are handed governs, and only a reading of that specific document (or advice on it) can tell you your position. Written by Mat Kennedy at The Construction Contracts Co.