AS 4000 general conditions of contract: what the form says, and why it matters to a subbie
AS 4000-1997 is the head contract between a principal and a builder on a large share of Australian construct-only projects. You will rarely sign it as a subcontractor, but it shapes the document you do sign: the liquidated damages rate, the defects period, the programme and the notice regime in your subcontract are usually written to sit underneath it. Knowing what the unamended form says gives you a benchmark, because the unamended form is noticeably fairer than most of what gets issued under its name. The form is copyright Standards Australia, so this page describes it rather than reproducing it.
What the drafting says
Figures read from publicly published documents analysed in the Australian Subcontract Index corpus, August 2026.
How it compares
Set the unamended form beside the Index and the direction of travel is obvious: every identifiable time bar in the contracts we have analysed is drafted as an absolute bar, where AS 4000's own notice clause expressly is not.
Termination for convenience appears in roughly nine in ten contracts in the Index. It is not in the standard form at all.
The amendments are rarely about the project. They are a standing schedule the principal's or builder's lawyers attach to every job.
What to do about it
Common questions
What is AS 4000 used for?
AS 4000-1997 is a general conditions of contract for construct-only work, used between a principal and a head contractor. It is administered by a Superintendent and is one of the most widely used head contract forms in Australia.
What is the difference between AS 4000 and AS 4902?
AS 4000 is construct only: the principal supplies the design. AS 4902 is the design and construct version, where the contractor takes on design responsibility. The two share most of their clause structure.
Does AS 4000 apply to me as a subcontractor?
Not directly. Your contract is the subcontract, commonly AS 4901 or the builder's own template. AS 4000 matters because the subcontract is usually drafted to pass its risks down to you, sometimes by reference to clauses you have never been given.
Is a late notice fatal under AS 4000?
Not under the unamended form, which says a late notice does not bar or invalidate the claim. It very often is fatal under the amended version you are actually handed, so search the special conditions for "condition precedent" and "barred".
Keep reading
- What should I check before signing a subcontract? →
- What is a time bar in a subcontract, and when does it kill the claim? →
- What's a reasonable liquidated damages rate in a subcontract? →
- The QBCC commercial template →
- AS 4901, as amended →
- The builder's own template →
- Purchase order terms →
- AS 4902 (design and construct) →
- AS 4903 (design and construct subcontract) →
- AS 2545 (older subcontract form) →
- The MBA NSW standard trade contract →
- All contract-form breakdowns →
General information for Australian subcontractors, not legal advice. Patterns describe publicly published documents analysed in the Index corpus, and standard forms are described from their published, unamended editions; the document you are handed governs, and only a reading of that specific document (or advice on it) can tell you your position. Written by Mat Kennedy at The Construction Contracts Co.