Not being paid on a Tasmanian job? There is a law built for exactly this. And in Tasmania, just knowing it is usually enough.
The Security of Payment Act. Built to get subbies paid in weeks, not years.
Step one. A valid payment claim. The work identified. The amount claimed. Served on time.
The builder then has ten business days to respond with a payment schedule.
Silence means the full claimed amount becomes payable. And the builder is limited at adjudication.
Adjudication runs through authorised nominating authorities. Determinations typically within ten business days of acceptance.
Here is the Tasmanian reality. Adjudication volumes are low. Which means a well founded claim, properly served, usually moves the money before any application is filed.
The standard suspension rights are there too. On notice, under the Act.
The windows are strict, and public holidays move real dates. Verify every deadline against the Act before you act.
Know your position before you pick the fight. Free tools below. And know what you're signing.