Variation notice template — the 90-second email that saves the claim
Verbal directions are directions - right up until it is time to pay for them. This template is the habit that beats the clause: a same-day email confirming the site direction as a variation, followed by the formal notice your contract requires. Send the first part before you leave site, every time the work changes.
- The builder's team directs a change on site - more scope, different materials, a redesign, out-of-sequence work
- You are asked to "just sort it while you're here"
- A drawing revision or RFI response changes the work you priced
PART 1 - SAME-DAY SITE CONFIRMATION (send before you leave site) Subject: Variation - [project name] - [short description] - [date] Hi [name], Confirming our discussion on site today ([date]) regarding [describe the change - e.g. additional GPOs to the level 2 meeting rooms / revised setout to grid B]. We are treating this direction as a variation under the subcontract. Formal notice and pricing will follow within the contract timeframes. Unless you advise otherwise, work will proceed on that basis. Regards, [name] [company] PART 2 - FORMAL VARIATION NOTICE (send within your contract's notice window) NOTICE OF VARIATION Contract: [subcontract title / number] Project: [project name] Date: [date] To: [head contractor], Attention: [contract administrator] 1. Notice is given under clause [X] of the subcontract that the following direction constitutes a variation to the works. 2. The direction: [describe the changed work]. Directed by [name / role] on [date], [verbally on site / by email / by drawing revision no. X]. 3. Effect on the works: [summary - added scope / changed materials / out-of-sequence working]. 4. Price: [amount if known, ex GST / to be advised - a detailed price will follow within [X] business days]. 5. Program: [no effect anticipated / an extension of time will be claimed separately if the variation delays the works]. 6. [Company] reserves its rights under the subcontract and at law. Signed: [name, position] [company]
Using it well
Common questions
Do I really need to send a variation notice for small changes?
Yes - the habit matters more than the amount. Small undocumented changes accumulate into large unpaid scope, and the same short notice window applies to a $500 change as to a $50,000 one. The Part 1 email takes 90 seconds.
What if the builder says a direction is not a variation?
Then you have a documented disagreement instead of a silent one - which is exactly where you want to be. Keep performing under protest if the contract requires it, keep records of the cost, and the notice preserves your claim.
Is a verbal direction on site enforceable?
Many contracts require variations to be directed in writing, which is why verbal directions so often go unpaid. Your same-day confirmation email converts the verbal direction into a written record - and gives the builder the chance to withdraw it in writing if they disagree.
Keep reading
General information and a starting-point template, not legal advice. Contracts and state Acts differ and change — verify clause numbers, statutory sections, notice periods and service requirements before use, and get advice on a live dispute. Nothing on this page is uploaded or stored. Built by Mat Kennedy at The Construction Contracts Co.