Extension of time notice template — serve it the day the delay starts
Every time bar we've been able to identify across the real subcontracts we analyse is drafted as absolute: miss the window and the entitlement is extinguished, regardless of who caused the delay. This notice is deliberately front-loaded - serve it the day the delay starts with the details you have, and let the particulars follow. A short imperfect notice inside the window beats a perfect one outside it.
- Anything delays the works - late access, late information, other trades, builder's design changes, weather, latent conditions
- You are even unsure whether it will delay completion - serve it anyway and let events decide
- A variation adds work that will take time, not just money
NOTICE OF DELAY AND CLAIM FOR EXTENSION OF TIME Contract: [subcontract title / number] Project: [project name] Date: [date] To: [head contractor], Attention: [contract administrator] 1. Notice is given under clause [X] of the subcontract of a delay to the works. 2. Cause of delay: [describe - e.g. access to level 3 not available from [date] as programmed / late issue of construction drawings for [area] / directed variation no. [X]]. The cause is not attributable to [subcontractor company]. 3. The delay commenced on [date]. [Subcontractor company] first became aware of the delay on [date]. 4. Activities affected: [activities / areas / trades affected]. 5. Extension claimed: [X] calendar days, or such further period as the delay continues. Further particulars, including program evidence, will be provided [within the contract timeframe / as they become available]. 6. Delay costs: [costs are being incurred and will be claimed separately / no claim at this stage - rights reserved]. 7. [Subcontractor company] reserves its rights under the subcontract and at law. Signed: [name, position] [company]
Using it well
Common questions
How long do I have to serve an EOT notice?
Whatever your contract says - and the windows are short. Across the contracts we've analysed, notice windows run as short as a few business days, and every identifiable time bar is drafted as absolute. Find your clause, write the number of days on the wall, and serve inside it.
Should I serve notice if the builder caused the delay and everyone knows it?
Especially then. Under an absolute time bar it does not matter who caused the delay - a late notice extinguishes the claim, and the liquidated damages clock can run against you for someone else's delay. Site conversations are not notice.
What if I'm not sure the delay will affect completion?
Serve the notice anyway and say the effect is being assessed. A notice for a delay that evaporates costs nothing; a missed notice for a delay that runs costs the entitlement.
Keep reading
General information and a starting-point template, not legal advice. Contracts and state Acts differ and change — verify clause numbers, statutory sections, notice periods and service requirements before use, and get advice on a live dispute. Nothing on this page is uploaded or stored. Built by Mat Kennedy at The Construction Contracts Co.