Retention on New South Wales subcontracts: what's normal, and what to watch
The market-normal position across the subcontracts we've analysed is retention of 5% of the contract sum - typically 10% of each payment until the cap is reached - with half released at practical completion and the balance at the end of the defects liability period. Drafting that holds 10% overall, ties release to the head contract, or restarts the defects period on every rectification is where subcontractors' money gets stuck.
The market position
Median retention in the contracts we've analysed is 5% of the subcontract sum. Ten per cent overall - the position some contracts open with - is double the market and worth pushing back on by that fact alone; subcontractors have negotiated it to 5%, or to two 2.5% bank guarantees in place of cash retention, on exactly that argument.
The stronger ask isn't always the percentage - it's the instrument. Bank guarantees keep the cash in your business; unconditional ones can still be called, but they beat cash deductions for cash flow on every job.
Release: where the real risk hides
Two clauses quietly extend retention past what the percentage suggests. Release tied to the head contract - "on practical completion under the Head Contract" - makes your money wait on a project completion you don't control. And a defects liability period that restarts whenever you rectify a defect can hold the final tranche years past the stated end date.
The positions to ask for: release keyed to your own practical completion and your own DLP, a fixed outside date regardless of rectifications, and release on request rather than on the builder's initiative.
The NSW angle
In NSW, retention money held from subcontractors on larger projects must be held in trust - a statutory protection against the builder's insolvency that most states don't offer.
Head contractors must pay subcontractors within 20 business days of the claim, retention money on larger projects must be held in trust, and work can lawfully be suspended after non-payment on two business days' notice.
Clause-by-clause risk report against New South Wales security of payment law in about 90 seconds.
Scan my subcontract freeFrequently asked questions
It appears in opening drafts, but it's double the market: median retention across the subcontracts we've analysed is 5% of the contract sum. The 10%-of-each-payment mechanic is normal; the overall cap is what to negotiate.
When your contract says - which is exactly the problem with drafting tied to the head contract or to a restarting defects period. Market position: half at your practical completion, the balance at the end of your own defects liability period, with a fixed outside date.
General information for Australian subcontractors, not legal advice. Statutory deadlines change and have exceptions - verify against the Act and current guidance, or with a construction lawyer, before acting on them.