The Construction Contracts Co.
Victoria Subcontract Guides
VIC scanner
Victoria · variations

Variations on Victoria subcontracts: getting changed work paid

Most variation money is lost between the site conversation and the paperwork. The standard subcontract lets the builder direct variations unilaterally, gives you a short written-notice window (as little as 2 business days in contracts we've analysed) with an absolute bar behind it, and lets the builder value the work where rates don't apply. Since Victoria's 15 April 2026 reforms, disputed variations can generally be pursued in a payment claim and at adjudication - the old claimable-variations restrictions are abolished.

The three clauses that take the money

Unilateral direction: "the subcontractor must comply with all variation orders" - you're bound to do the work before the price is agreed. Positions builders have accepted: variations agreed in writing before they bind, or a cap (bound only within the general scope, up to a stated percentage of the contract sum).

The notice time bar: a direction you consider a variation must be notified in writing inside the window or the claim is lost - 2 business days appears in real contracts. And valuation: "reasonable rates as determined by the Contractor" puts the price of your work in the other party's hands; a schedule of rates incorporated into the contract, sitting high in the order of precedence, is the fix.

The VIC angle

Victoria is the state where the law just moved. For payment claims served from 15 April 2026, the old excluded-amounts and claimable-variations regimes are abolished - disputed variations, damages and time-related costs can now generally be included in a payment claim and pursued at adjudication. Pre-reform advice that variations couldn't be adjudicated in Victoria no longer applies to new claims.

The 90-second habit

Before leaving site on the day anything changes: one email. "Confirming we discussed [the change] on site today. We're treating this as a variation. Formal notice and pricing follow within the contractual timeframe. Work proceeds on that basis unless you advise otherwise." It anchors the date, creates the record, and starts you inside whatever window the contract sets.

From the Australian Subcontract Index - live data
100%
have time bars that extinguish the claim entirely · 39 of 39
From 54 subcontracts analysed to date · see the full Index
Where does your contract sit?

Clause-by-clause risk report against Victoria security of payment law in about 90 seconds.

Scan my subcontract free

Frequently asked questions

Do I have to do variation work before the price is agreed?

Under standard drafting, yes - the direction binds first and valuation follows. That's why the pre-signature ask is a written-agreement requirement or a cap, and the on-site protection is same-day written confirmation of every direction.

Can I claim an unpaid variation through security of payment in VIC?

Yes - for claims served from 15 April 2026, the reformed Act generally allows disputed variations in a payment claim and at adjudication. The old restrictions are abolished.

Keep reading
Do variations need to be in writing for me to get paid?What is a time bar in a subcontract — and when does it kill the claim?What makes a progress claim one that actually gets paid?How long can a builder take to pay a subcontractor in Victoria?Time bars in Victoria subcontracts: what you lose, and whenRetention on Victoria subcontracts: what's normal, and what to watchHow adjudication works in VictoriaNot being paid in Victoria: when can you lawfully stop work?

General information for Australian subcontractors, not legal advice. Statutory deadlines change and have exceptions - verify against the Act and current guidance, or with a construction lawyer, before acting on them.